ESDSWG Reuse > Activities  

Activities

Modify settings and columns
Planned WG activites for the current year.
  
View: 
Sort by AttachmentsUse SHIFT+ENTER to open the menu (new window).
DescriptionFilter
Expand/Collapse Topic : Data Life Cycle ‎(1)
Work with "new" DLC group to help with persistent (re)use areasUse SHIFT+ENTER to open the menu (new window).
Not Started(2) Normal
Changed priority from high to normal based on April monthly telecon discussion -- can help the ESIP DLC cluster on issues related to reuse as appropriate, don't need to focus on them ourselves right now.
2009
Expand/Collapse Topic : Decadal Survey ‎(2)
Tie reuse efforts to the decadal survey missionsUse SHIFT+ENTER to open the menu (new window).
Not Started(2) Normal
Changed priority from high to normal based on April monthly telecon discussion. Agreed this would be nice to do, but other activities are higher priority; can try to find appropriate interfaces to the missions as a starting point though.
2009
Prepare for reuse as key part of (and asset for) new missionsUse SHIFT+ENTER to open the menu (new window).
Not Started(2) Normal
Changed priority from high to normal based on April monthly telecon discussion. Agreed this would be nice to do, but other activities are higher priority.
2009
Expand/Collapse Topic : Incentives ‎(3)
Continue to work to develop a NASA reuse award processUse SHIFT+ENTER to open the menu (new window).
Not Started(1) High
Working towards a NASA-level award to complement the Reuse WG's award. Should also consider a Goddard Center-level award.
2009
Run peer recognition award processUse SHIFT+ENTER to open the menu (new window).
In Progress(1) High
50%
Nomination deadline has passed; now seeking volunteers to participate in the review/selection process, to be completed by the end of August.
Summer
Work on recommendation/justification for HQ to develop a funding opportunity to make assets/components reusableUse SHIFT+ENTER to open the menu (new window).
Not Started(2) Normal
This could provide leverage for RES funding -- need a place to catalog/store and distribute the assets that are being made reusable.
2nd half 2009
Expand/Collapse Topic : Metrics ‎(3)
Assess effort required to package assets for reuseUse SHIFT+ENTER to open the menu (new window).
In Progress(1) High
10%
* Quantify benefits of open source release of assets -- 1st half 2009
* Work on small components, if different from large ones in tech. transfer process, how? -- first half 2009
* Possible use of RES to collect metrics (reuse in producing artifacts, savings by reusing artifacts) -- second half 2009
* Develop impact metrics from peer-recognition award recipients -- second half 2009
# Summarize NPP reuse case study for portal web site, as an impact metric -- Jan 2009; completed
2007 - 2009
Assess effort required to make assets available for reuseUse SHIFT+ENTER to open the menu (new window).
In Progress(1) High
10%
Release/distribution is closely related to packaging -- WG members are working on examining the release process at NASA and other organizations (e.g., ORNL).
2nd half 2009
Continue to generate/analyze statistics for portal web siteUse SHIFT+ENTER to open the menu (new window).
In Progress(2) Normal
Use NetInsight stats
Continuous
Expand/Collapse Topic : Policy ‎(1)
Continue working with IPP Office to facilitate software release processUse SHIFT+ENTER to open the menu (new window).
In Progress(1) High
25%
Guideline document and FAQ on transfer process complete. Continuing conversation with IPP Office to provide additional guidance. Need to work to understand and change the process, lower the barriers for certain types of software (if possible).
Consider selecting some proof-of-concepts in the NTR process (e.g., ISFS). Consider meeting with Chris Lynnes, who is having trouble getting software through the process, to discuss possible barriers, causes for delays, etc. and use this to help in discussions with the IPP Office.
2007 - 2009
Expand/Collapse Topic : Portal ‎(5)
Provide more portal content and keep up to dateUse SHIFT+ENTER to open the menu (new window).
In Progress(2) Normal
Continuous
Promote reuse portal to communityUse SHIFT+ENTER to open the menu (new window).
In Progress(2) Normal
Continuous
Add RES roadmap and later RES deployment scheduleUse SHIFT+ENTER to open the menu (new window).
In Progress(2) Normal
10%
Included screen shots of prototype RES on portal web site to help show bigger picture of planned system and its capabilities. May need to do more work on this activity.
1st half 2009
Enhance discovery of reusable assetsUse SHIFT+ENTER to open the menu (new window).
In Progress(3) Low
10%
Created prototype demonstration of gonzui source code search engine, but not available now on new Plone site.
Continuous
Develop approaches for bottom-up reuseUse SHIFT+ENTER to open the menu (new window).
Waiting on someone else(3) Low
95%
Produced guidelines from presentations and discussion at 5th ESDS WG Meeting posted as final.  One document still not produced.
2006 - 2009
Expand/Collapse Topic : Promote ‎(5)
Examine and promote reuse of mediaUse SHIFT+ENTER to open the menu (new window).
Not Started(1) High
Examples include images or parts of images used in artists' renditions as well as functional imagery such as buttons for web sites.
May need to verify if this is reuse (integration into another context) and scope the activity if it is -- what media can be reused and how, what our work product for this activity will be (guidelines for media reuse?).
Made high priority in consideration of discussion about this on April monthly telecon.
2nd half 2009
Develop reuse readiness levels (RRLs)Use SHIFT+ENTER to open the menu (new window).
In Progress(1) High
20%
# Produce a full document with background, justification, etc. -- Dec/Jan, essentially done
* Develop use cases for developer/submitter and reuser -- Jan/Feb, in progress
* Analyze RRLs for possible break points -- in progress
* Use RRLs to assess real software (try them out) -- Feb/Mar
* Use feedback from above to revise RRLs -- Mar/Apr
* Plan for face-to-face meeting ~April 2009 to finalize levels -- Apr/May
Original plan to complete around spring has slipped significantly due to addition of break point analysis and need for increased input from support team and WG on this topic.
Winter/Spring
Prototype a process for facilitating reuse through mentoringUse SHIFT+ENTER to open the menu (new window).
Not Started(2) Normal
Discuss topic to determine particular activities and topics; hold a kick-off meeting/telecon to get this started.
2008-2009
Hold special sessions at upcoming meetingsUse SHIFT+ENTER to open the menu (new window).
In Progress(2) Normal
40%
Consider holding sessions at:
# AGU 2009 Fall (reuse session proposal accepted)
* Winter ESIP Meeting
See meeting deadlines
Continue publications in journals and presentations at conferencesUse SHIFT+ENTER to open the menu (new window).
In Progress(2) Normal
60%
# Presented at Winter ESIP (Jan.)
* Preparing ESSI Workshop paper for publication in Springer's Earth Science Informatics journal
# Completed chapter for IN-TECH's book Aerospace Technologies Advancements; now doing proof-readings to prepare for October publication of book
* Submitted paper on RRL uses for ICSR was rejected; considering option to present poster and where full paper may be resubmitted
* Considering topics for for Fall AGU submission (due Sept. 3, meeting in Dec.)
As per meeting deadlines
Expand/Collapse Topic : RES ‎(8)
Develop RES implementation planUse SHIFT+ENTER to open the menu (new window).
Not Started(1) High
Need to develop a plan for deployment of RES (NASA-only use at first, with aim towards general public use later).
1st half 2009
Deploy prototype RES for internal NASA useUse SHIFT+ENTER to open the menu (new window).
Not Started(1) High
Can begin after the WG agrees prototype is complete and it has been formally tested by the WG.
2nd half 2009
Complete RES Policies document and vet policies (internal and external)Use SHIFT+ENTER to open the menu (new window).
In Progress(1) High
50%
Drafted, reviewed, revised, and approved current version of RES Policies document; preparing for review by ESDS WG Chair, NASA HQ, and other applicable parties (e.g., IPP Office, legal office)
1st half 2009
Complete RES Test Plan and test RESUse SHIFT+ENTER to open the menu (new window).
In Progress(2) Normal
50%
Current draft of test plan being reviewed and updated as needed.
Winter/Spring
Build RES for internal NASA useUse SHIFT+ENTER to open the menu (new window).
In Progress(2) Normal
90%
Release 1 of prototype RES essentially complete; minor updates being made as needed. Official completion pending completion of Test Plan and formal testing of prototype against the plan.
2007 - 2009
Submit RES architecture study and get HQ's feedbackUse SHIFT+ENTER to open the menu (new window).
In Progress(2) Normal
95%
Document submitted to HQ; working to schedule time for presentation to NASA HQ.
2007 - 2008
Develop and test RES prototype architecturesUse SHIFT+ENTER to open the menu (new window).
Completed(2) Normal
100%
Tested architecture study prototypes and decided to use XOOPS with modifications for building a prototype RES.
2007
Submit RES trade study and get HQ’s feedbackUse SHIFT+ENTER to open the menu (new window).
Waiting on someone else(3) Low
100%
Waiting for official response from HQ -- expected to receive a formal, written response, but this may not be coming
Expand/Collapse Topic : Services ‎(2)
Consider role of SOA and web services in WG activitiesUse SHIFT+ENTER to open the menu (new window).
Not Started(1) High
Suggestion by Martha Maiden at 2008 ESDSWG Meeting; can include other newer technologies (e.g., cloud computing). Need to identify which technologies to consider; also need to avoid overlapping any Tech. Infusion work in these areas.
Discuss topic to determine particular activities and topics; hold a kick-off meeting/telecon to get this started.
Changed priority from normal to high based on April monthly telecon discussion.
Apr/May kick-off
Identify potential to promote reuse of web servicesUse SHIFT+ENTER to open the menu (new window).
Not Started(3) Low
Possible area of collaboration with other WGs.
Discuss topic to determine particular activities and topics; hold a kick-off meeting/telecon to get this started.
2008 - 2009